investigation

Who paved Atlas Peak Road, and how Napa paid for it

Supplier invoices identify the asphalt, timesheets identify the crew, and a later board award identifies the upper stretch of road and the money transferred to pave it.

Napa County crews logged paving work on Atlas Peak Road in 2018 and 2019. Seventeen Syar Industries invoices carried the Atlas Peak job description. Fifteen amounts total $174,257.23. Two entries transcribed from scans bring the provisional total to $214,706.25.

The year totals in the released analysis are $21,410.47 in 2018 and $193,295.78 in 2019. The amounts awaiting image confirmation are $20,154.41 on invoice 753436 and $20,294.61 on invoice 755310. Fifteen crew timesheets name Road 340 and identify paving or paving-box work. The milepost fields on the cited sheets are blank, so the sheets locate the work on the road without specifying each stretch.

Syar invoices coded to Atlas Peak1
Syar invoices coded to Atlas Peak
InvoiceDateAmountReading
683661Apr 17, 2018$10,145.51Amount as transcribed from claim
694897Jul 10, 2018$11,264.96Amount as transcribed from claim
749914Sep 26, 2019$456.86Amount as transcribed from claim
750042Sep 26, 2019$12,844.51Amount as transcribed from claim
750234Sep 27, 2019$13,521.46Amount as transcribed from claim
753436Oct 2, 2019$20,154.41Scan transcription, amount unconfirmed
753647Oct 22, 2019$19,835.53Amount as transcribed from claim
753927Oct 23, 2019$12,959.93Amount as transcribed from claim
754058Oct 24, 2019$19,290.81Amount as transcribed from claim
754298Oct 25, 2019$9,181.53Amount as transcribed from claim
754935Oct 31, 2019$482.30Amount as transcribed from claim
755101Nov 1, 2019$156.98Amount as transcribed from claim
755302Nov 4, 2019$221.09Amount as transcribed from claim
755310Nov 4, 2019$20,294.61Scan transcription, amount unconfirmed
756179Nov 4, 2019$19,437.40Amount as transcribed from claim
755688Nov 6, 2019$24,961.11Amount as transcribed from claim
756009Nov 7, 2019$19,497.25Amount as transcribed from claim

The 2023 contract covered a defined 2.7 miles

The later East Central Paving project had three phases. County awards totaled $6,841,558 across Argonaut Constructors, O.C. Jones and Martin Brothers Construction. In June 2023 the county awarded Martin Brothers $1,305,728 for Phase Three, the final stretch to the cul-de-sac. Total project cost was $1,636,587.

The budget transferred $483,229 from the Calistoga Area Paving Project and $423,358 from accumulated capital outlay. Together those amounts make $906,587. Approximately $730,000 remained available from the PG&E settlement for the upper-road project.

The June 27 consent vote was unanimous, with Cottrell, Gallagher, Gregory, Pedroza and Ramos voting yes. The specifications include geotechnical photographs near 4110 Atlas Peak, which the Pedrozas later acquired on April 18, 2025. The purchase followed the vote by almost two years.

The December 14, 2023 federal subpoena listed Atlas Peak paving first. The invoices, timesheets and Phase Three contract answer separate questions about the material bought, the labor performed and the later work authorized.

Timesheets and related road contracts2

The 2018 claims were coded to Syar vendor 17242, Fund 2040 and account 53360. The road-crew sheets record paving-box work in April 2018 and overtime on October 21–22, 2019. They do not supply delivery points for each invoice.

Other files in the county production concern the RDS 20-44 LNU fire debris contract, a $697,760 low bid, an Argonaut asphalt overage change order for $67,974.38 and striping contracts RDS 21-27 and 22-02. Their inclusion in one archive does not make them all Phase Three costs.

How the three paving awards fit together2

The county received $33,954,044 in the PG&E settlement and allocated $16 million for roads on July 28, 2020. East Central Paving project 21067 covered multiple roads and contracts. On August 10, 2021, the board awarded Argonaut Constructors $3,297,296, with Pedroza serving as board chair and signing officer. O.C. Jones received $2,238,534 on June 7, 2022. Martin Brothers received $1,305,728 on June 27, 2023. Those three awards add to $6,841,558.

The 2018–19 Syar invoices predate that settlement allocation. They document materials coded to Atlas Peak. The later Phase Three contract specifies the upper-road limits. These dates and descriptions keep the earlier material purchases distinct from the later capital project.

Related reporting

Syar-linked companies gave to Pedroza before and after a quarry vote

Two federal subpoenas ten days apart asked Napa for two different sets of records

How the 4110 Atlas Peak purchase led back to Vinedos

All In: The Pedroza Record — complete series and reference tables

References (4)
  1. Atlas Peak invoices, crew timesheets and contracts — Napa County records release, 26-1527
  2. Award of East Central Paving Project, Phase Three — Napa County Board of Supervisors
  3. East Central Paving Phase Three budget — Napa County Public Works
  4. Board minutes, June 27, 2023 — Napa County Board of Supervisors